7-10-2013| Viaduct Project Underway

On Monday, July 8, 2013, the viaduct was shut down as Railworks crews mobilized their equipment after the final train. Cable tray and cable tray supports were installed up to the edge of the river, which covers more than 60 percent of the open deck structure of the bridge. Already, the project is approximately 12% complete.

By Monday, July 22, crews are scheduled to install the remaining cable tray and supports. Meanwhile, safety netting is in place up to the edge of the river and the installation is scheduled to be completed by July 24.

Demolition of the track structure on the deck portion of the viaduct is also underway and is scheduled to be completed by Friday, July 26.