Darby Transportation Center Renovation & Expansion

P1C-6

100%
completed

Delaware County

Engineering/Design Firm: Burns Engineering

Improvements to enhance passenger services and operational efficiency at this bus and trolley transportation center will include new platforms, shelters, windscreens, canopies.

Contracts Awarded

General Contractor | Gateway Project Management LLC
$1,229,750

Electrical Contractor | Vanalt Electrical Construction
$285,900

DBE Information

19% | General Contractor
8% | Electrical Contractor

What's Happening

  • 06-11
  • New platforms, shelters, windscreens & canopies are successfully installed. Dedication for the completed project was held on Friday, June 17th.

  • 08-10
  • Dedicated one-way bus transitway connecting Main Street & MacDade Blvd. finished.

    Canopy and enclosed passenger shelter with radiant heating built.

    New crosswalks and concrete sidewalks; newly paved roadway completed.

    Improved lighting and directional signage installed.

  • 07-10
  • Site landscaping improved with the addition of ornamental fencing; pedestrian walkways; landscaping & historical markers installed.

Project Chronology