Airport Line


Right Of Way Fencing

P1-4

100%
completed

Philadelphia County

Engineering/Design Firm: SEPTA

Install replacement fencing and extend the existing right-of-way fence between milepost 4.06 near the AMTRAK Northeast Corridor to milepost 7.95 at the Viaduct over I-95. The project also includes brush-cutting.

Contracts Awarded

General Contractor | Rockport Construction Company
$2,139,500

DBE Information

13% | Overall DBE Goal

What's Happening

  • 05-10
  • Contractor Work: Physical project completed.

    Contractual Info: Payment invoice for Change Order #2 work was approved and submitted for payment. Shared Utility companies have been notified of gates, requested to update their locks.

    Anticipated Work: Final payment to contractor.

  • 04-10
  • Contractor Work: Punchlist item - grounding @ 95%. Materials still on order. Gates installed. System swept to remove leftover construction materials. Locks received.

    Contractual Info: Submitted closeout documents to Contract Administrator 4/9/10. Approved invoice for payment 4/13/10. Change order #2 has been approved and executed in the amount of $85,300, as of 4/8/2010. Total new Contract Price: $2,229,600.

    Anticipated Work: Complete remainder of grounding; items on order, awaiting delivery. Shared Utility companies to be notified of gates, to update their locks. Final Walk to check punchlist items to be held after remainder of grounding clamps installed. Install locks during final walk.

  • 03-10
  • Contractor Work: 61st to 63rd St. - Fabric being secured at this location. Approx. 95% completed. Field work continuing; grounding @ 90%. Awaiting final shipment of clamps from vendor. Contractor installed fence at tie in on north end, OB side. Gates installed. Beginning system sweep to remove leftover materials. Contractor to complete punchlist.

    Contractual Info: Prepared punchlist.

    Anticipated Work: Complete remainder of grounding; items on order, awaiting delivery. Shared Utility companies to be notified of gates, to update their locks. Begin Substantial Completion Documentation. Final Walk with contractor. Install Locks.

Project Chronology
Fact Sheet

Photos