Lansdale/Doylestown Line


Melrose Park, North Hills, Penllyn Bridge Rehabilitation

P1-9A; P1-9B & P1-9C

100%
completed

Montgomery County

Engineering/Design Firm: HNTB

Bridge 8.38: Repair joints between girders and replace deck waterproofing to stop water leaks on this precast concrete and circa 1987 box girder structure spanning Valley Road adjacent to the Melrose Park Regional Rail Station.

Bridge 13.04: Repair deteriorating concrete fascia, parapets, and walls; replace waterproofing for this 1930's era bridge spanning over North Hills Ave adjacent to the North Hills Regional Rail Station.

Bridge 18.87: Repair deteriorating concrete fascia, parapets, and walls; replace waterproofing for this 1930's era bridge over Penllyn Pike near the Penllyn Regional Rail Station.

Contracts Awarded

General Contractor | Rockport Construction Company
$2,905,395

DBE Information

17% | Overall DBE Goal

What's Happening

  • 08-10
  • ...

Project Chronology
Fact Sheet