Media/Elwyn Line


Track Bed Stabilization

P1C-1

100%
completed

Delaware County

Engineering/Design Firm: URS

Stabilize areas of slope and track bed failure near milepost 17 caused by heavy rains and poor soil conditions. Temporary repairs have been made however permanent repairs must be completed to support the planned restoration of rail service between Elwyn and Wawa. Project work includes construction of retaining walls between Lungren Rd (MP 17.13) and Lenni Road (MP 17.35). In addition, deteriorated catenary structures and retaining walls in the area of the slope failure will be repaired or replaced.

Contracts Awarded

General Contractor | Alan A. Myers, Inc.
$9,468,500

DBE Information

18% | Overall DBE Goal

What's Happening

  • 07-10
  • The Contractor continues punchlist work.

  • 06-10
  • The Contractor has begun punchlist work.

  • 05-10
  • The installation of the track structure in the entire project area is complete. The track was returned to service May 5th, 2010. The Contractor has begun rail bonding and the installation of catenary structures.