Wilmington/Newark Line


Folcroft Station Building Rehabilitation

P2-15C

100%
completed

Delaware County

Engineering/Design Firm: Gannett Fleming

Rehabilitate and paint existing station building exterior; upgrade mechanical and electrical systems to bring the existing station building into compliance with building code and energy efficiency requirements.

The contractor bid also includes work on the Morton (P2-15D) and Clifton-Aldan (P2-15E) Station buildings.

These station buildings date back to the 1910s and have not had any significant renovations.

This contract also includes Morton and Clifton Stations.

Contracts Awarded

General Contractor | Ernest Bock & Sons
$1,034,650

Electrical Contractor | Alfred J. Frey II, Inc.
$82,195

Mechanical Contractor | The Plumber, Inc.
$89,900

DBE Information

13% | General Contractor
8% | Electrical Contractor
6% | Mechanical Contractor

What's Happening

  • 10-11
  • Folcroft Station reconstruction project earns a 2011 Preservation Achievement Award from the Preservation Alliance for Greater Philadelphia.

  • 06-11
  • Rehabilitation & painting is successfully completed at Folcroft Station, while its mechanical & electrical systems have been upgraded to comply with building code and energy efficiency requirements. Contracts for the project are in the close-out phase.

  • 12-10
  • All work is complete at Folcroft Station.