Warminster Line


Warminster Station Roof Replacement

P1-5A

100%
completed

Bucks County

Engineering/Design Firm: SEPTA

Remove and replace existing roof with a modified bitumen roof, new flashing, and new fascias.

This contract also includes the Lansdale Substation roof replacement.

Contracts Awarded

General Contractor | Plato Construction Corp.
$165,000

DBE Information

6% | Overall DBE Goal

What's Happening

  • 04-10
  • Project completed. Closeout Done. Final Invoice Approved.

  • 03-10
  • All work on site completed. Substantial Completion Notification Processed.

  • 02-10
  • Minor Punch List items remain to be done.