Bucks County
Engineering/Design Firm: SEPTA
Remove and replace existing roof with a modified bitumen roof, new flashing, and new fascias.
This contract also includes the Lansdale Substation roof replacement.
General Contractor | Plato Construction Corp.
$165,000
Project completed. Closeout Done. Final Invoice Approved.
All work on site completed. Substantial Completion Notification Processed.
Minor Punch List items remain to be done.