Attention: Paoli/Thorndale Riders (R5)
Phase 1 Is Ending. Phase 2 Begins August 13,
with a new schedule effective August 12, 2007
 

Track Work
Service Alterations Phase 1
May 7, 2007 – Mid-August 2007

This is a joint Amtrak, PennDot, SEPTA project

SEPTA and Amtrak are conducting track renovation work. 

Following the new May 6th schedule, Amtrak began work on Monday, May 7th installing concrete ties and continuous-welded rail on Track #1 between Paoli and Bryn Mawr.

Phase 2: New Schedule
On August 13, Phase 2 of this work will move to Track #4 (outbound service) between Paoli and Overbrook Stations, and will continue through November.  New schedules will go into effect on Sunday, August 12, 2007.
Phase 2 Information

At the completion of this project, in December 2007, customers will experience an improved ride quality and fewer future maintenance projects as a result of the continuous welded rail and concrete tie installation. SEPTA riders will also enjoy quieter train operations, increased travel speeds, reduced travel times, and enhanced service reliability.

 

Beginning May 7th and continuing through the middle of August, customers should note the following service changes due to Amtrak track renewal work:

Weekday, Peak Inbound Service

  • Service will operate from Track #2 between Paoli and Bryn Mawr Stations
  • Customers will be required to cross to Track #2 only at designated areas
  • Most but not all weekday, inbound train departure times will be earlier to account for travel time in the work zone and coordination with Amtrak services
  • Due to track capacity limits, some peak train service will be combined 

    Departing Station
    (to Center City)
    Current Schedule
    Peak-Weekday
    May 6th Schedule
    Peak-Weekday
    Arrive
    Suburban
    Malvern (#514) 5:16 a.m. 5:12 a.m. 6:07 a.m.     
    Malvern (#516) 5:51 a.m. 5:47 a.m. 6:44 a.m.
    Thorndale (#518) 5:52 a.m. 5:46 a.m. 6:56 a.m.
    Bryn Mawr (#520) 6:42 a.m. 6:37 a.m. 7:11 a.m.
    Thorndale (#9522) 6:15 a.m. 6:10 a.m. 7:21 a.m.
    Bryn Mawr (#4208) 7:09 a.m. 7:04 a.m. 7:38 a.m.
    Malvern (#524) 6:59 a.m. 6:54 a.m. 7:44 a.m.
    Thorndale (#9526) 6:52 a.m. 6:50 a.m. 7:49 a.m.
    Bryn Mawr (#4624) 7:33 a.m. 7:30 a.m. 8:04 a.m.
    Malvern (#9530) 7:19 a.m. 7:18 a.m. 8:08 a.m.
    Thorndale (#534) 7:11 a.m. -- --
    Thorndale (#9536) -- 7:12 a.m. 8:27 a.m.
    Thorndale (#9538) 7:25 a.m. -- --
    Paoli (#9538) -- 7:42 a.m. 8:35 a.m.
    Bryn Mawr (#9008) 8:13 a.m. -- --
    Thorndale (#9008) -- 7:35 a.m. 8:43 a.m.
    Malvern (#540) 8:00 a.m. -- --
    Malvern (#9540) -- 7:57 a.m. 8:47 a.m.
    Bryn Mawr (#9010) 8:32 a.m. 8:29 a.m. 9:02 a.m.
    Thorndale (#9542) 8:13 a.m. 8:09 a.m. 9:29 a.m.

  • In mid-July, work on Track #1 will move between Bryn Mawr and Overbrook Stations.  Customers traveling from these stations will board from Track #2. When this change takes place, customers boarding between Paoli and Bryn Mawr will return to Track #1.
 

Midday/Weekday Inbound Service

  • Off-peak service frequency will decrease to 60 minutes

    Departing Station
    To Center City

    Current Schedule
    Midday-Weekday

    May 6th Schedule
    Midday-Weekday

    Arrive
    Suburban

    Malvern (#544) 8:57 a.m. --         --
    Thorndale (#546) 9:10 a.m. -- --
    Thorndale (#9546) -- 9:14 a.m. 10:30 a.m.
    Malvern (#548) 9:56 a.m. -- --
    Thorndale (#550) 10:10 a.m. -- --
    Thorndale (#9550) -- 10:14 a.m. 11:30 a.m.
    Malvern (#552) 11:00 a.m. -- --
    Thorndale (#554) 11:10 a.m. -- --
    Thorndale (#9554) -- 11:14 a.m. 12:30 p.m.
    Malvern (#556) 12:00 p.m. -- --
    Thorndale (#558) 12:10 p.m. -- --
    Thorndale (#9558) -- 12:14 p.m. 1:30 p.m.
    Malvern (#560) 1:00 p.m. -- --
    Malvern (#562) 1:30 p.m. -- --
    Malvern (#9562) -- 1:34 p.m. 2:30 p.m.
    Malvern (#564) 2:00 p.m. -- --
    Malvern (#566) 2:30 p.m. -- --
    Malvern (#9566) -- 2:25 p.m. 3:20 p.m.
    Thorndale (#568) 2:40 p.m. 2:35 p.m. 3:50 p.m.

  • Customers from Paoli/Thorndale traveling towards Lansdale/Doylestown will need to transfer in Center City for connecting train service
  • Customers traveling beyond Glenside may experience transfer times of up to 44 minutes 
 

Midday/Weekday Outbound Service

  • Off-peak service frequency will decrease to 60 minutes
  • Platform boarding locations will remain the same, but some outbound, AM midday, weekday train times and destinations will change, please check the May 6th schedule for details.

    To Paoli/Thorndale

    Current Schedule
    Midday-Weekday

    May 6th Schedule
    Weekday

    Service Change
    Midday-Weekday

    Suburban (#513) 8:12 a.m. 8:12 a.m. Extended to Thorndale
    Suburban (#515) 8:45 a.m. 8:45 a.m. Ends at Malvern
    Suburban (#517) 9:15 a.m. 9:15 a.m. Extended to Thorndale
    Suburban (#519) 9:45 a.m. 9:45 a.m. Ends at Malvern
    Suburban (#521) 10:15 a.m. 10:15 a.m. Becomes #9521
    – extended to Thorndale
    Suburban (#523) 10:45 a.m. --  
    Suburban (#525) 11:15 a.m. 11:15 a.m. Becomes #9525
    – extended to Thorndale
    Suburban (#527) 11:45 a.m. --  
    Suburban (#529) 12:15 p.m. 12:15 p.m. Becomes #9529
    Suburban (#531) 12:45 p.m. --  
    Suburban (#533) 1:15 p.m. --  
    Suburban (#9533) -- 1:09 p.m.  
    Suburban (#535) 1:45 p.m. --  
    Suburban (#537) 2:15 p.m. 2:15 p.m. Becomes #9537
    Suburban (#539) 2:45 p.m. --  
    Suburban (#541) 3:15 p.m. 3:15 p.m. Becomes #9541
    Suburban (#543) 3:45 p.m. 3:50 p.m. Becomes #9545

  • Some PM peak and evening trains will also be adjusted, please check the schedule.
 

Weekend Inbound/Outbound Service

  • Inbound train service will depart earlier and outbound trains will depart later than the current schedule times to accommodate track work on the Lansdale/Doylestown side of the line.  Please check the schedule for details.
Phase 2 Information
New Paoli/Thorndale (R5) Schedule, August 12, 2007
Phase 2 Operations, August 13-November, 2007

For further information please call 215-580-7800 or check the Travel Advisory for updates.
For complete information about Amtrak service please go to their website www.amtrak.com or call 1-800-USA-RAIL (1-800-872-7245).

  Contact Us